Shutdown Planning Guide

When a plant stops production for maintenance or an equipment change, the lifting work needs to fit into a wider sequence of deliveries, trades and handovers. Organising crane hire for plant shutdowns in Adelaide starts with a clear scope: what needs to move, where it needs to go and when each area will be ready.

This guide helps facility managers prepare that information and coordinate the lifting component of a shutdown. For enquiries about a specific project, see United Cranes’ plant shutdown support.

1. Define the lifting scope before booking the crane

Build a lift list for the shutdown rather than relying on a single description such as “replace machinery”. Separate removal, unloading, positioning and any later return lifts. Give each item a reference that appears on the equipment drawings, delivery schedule and work programme.

For each item, gather:

  • Confirmed weight and dimensions, with supporting manufacturer information or drawings.
  • Details of lifting points and any specialist handling requirements for review by the lifting team.
  • The current position, proposed landing position and available access.
  • The work that must be finished before the lift, and the trade or site representative who confirms readiness.
  • Whether the item will leave site, remain in a laydown area or be reinstalled later.

Flag missing information early. A provisional weight or an unconfirmed delivery date should remain an open item in the programme, rather than quietly becoming an assumption.

2. Choose crane options around the load and the site

A crane’s headline capacity alone does not establish whether it suits a shutdown lift. The lifting provider needs to assess the load at the required working radius, the crane configuration, the travel or setup area and the surrounding obstructions. United Cranes’ lift planning services provide a relevant starting point for discussing these requirements.

A Franna pick-and-carry crane may be an option where a load needs to travel around a site, subject to assessment of the route and operating conditions. A compact mobile crane may be worth considering where access is restricted. Neither option should be selected simply because the building or work area is small.

For work inside or beside an industrial building, provide doorway dimensions, headroom, floor or ground information, overhead services and the proposed access route. Indoor suitability, including ventilation and any site-specific restrictions, must be assessed for the actual equipment and work. A compact footprint does not automatically make a crane suitable for indoor use.

3. Coordinate crane time with deliveries and trade handovers

Work backwards from the planned lift windows and identify their dependencies. Equipment arriving on time is only one part of readiness. The receiving area, access route and people responsible for the handover also need to be available.

  1. Before mobilisation: confirm the lift scope, site contact, access arrangements and outstanding information with the crane provider.
  2. Before the lift window: confirm delivery progress and completion of the prerequisite work with the responsible contractors.
  3. At the handover: use a named site representative to confirm that the work area is ready for the lifting team.
  4. After positioning: hand the equipment over to the relevant installation or maintenance team and confirm whether another lift is still required.

Keep one current schedule and nominate who communicates changes. If a delivery slips or an earlier job runs late, tell the crane provider before the agreed mobilisation or lift window wherever possible. Agree how changes and standby arrangements will be handled when discussing the booking, rather than assuming they are included.

4. Plan site documentation and responsibilities

Confirm induction requirements, site access permissions, relevant work permits and the documents the lifting team needs before arrival. The site and lifting teams should agree responsibilities, communication arrangements and how the lift area will be separated from other work.

Where equipment must be disconnected or isolated, identify the authorised site or trade personnel responsible for that work and its handover. Crane hire should not be treated as approval to proceed with maintenance or restart the plant.

The lift procedure needs to address the actual crane, load and conditions, including ground support, working radius, rigging, obstructions and weather limits. Safe Work Australia’s General Guide for Cranes explains the role of documented lifting procedures and clear communication. Use the site’s approved procedures and competent lifting personnel to determine the controls for the job.

5. Test the sequence with a hypothetical equipment change

The following is a hypothetical planning example, not a description of a completed United Cranes project.

Consider a facility replacing an HVAC unit during a shutdown. The programme needs to connect the removal of the old unit, delivery of the replacement, preparation of its landing position and the installation team’s handover. If the replacement is delayed, the coordinator needs to review the sequence with the lifting provider and affected trades before committing to the next lift.

A conveyor-section replacement raises a similar question: where will the removed section go while the replacement is being positioned? Planning the laydown area and transport movement in advance helps the team identify conflicting use of the same space. The equipment weight, lifting method and crane choice still require a separate assessment.

6. Include transport and the final handover in the booking brief

If machinery is being delivered or removed, coordinate the equipment transport arrangements with the lifting programme. Confirm vehicle access, unloading locations, contact details and who will communicate a changed arrival time. Keep the route and laydown area clear of competing deliveries through the agreed site arrangements.

Before requesting a quote, bring together the site address, shutdown dates, lift list, drawings, access photographs, delivery information and any known restrictions. Identify which details are confirmed and which still need review. Ask the provider to clarify the proposed scope, availability and any additional information needed for planning.